Transforming Community Spaces Through Equitable Collaboration Toolkit

4.5 Tools for Responsive Engagement
Conducting the Engagement Process
In Brief

Too many communities experience their governing authorities as distant, uncaring, and out of touch. A process may be wholly inclusive of a wide array of participants and views, but such inclusion needs to result in responses that demonstrate that participation has been valued. Otherwise the process breeds resentment and withdrawal.

Why This Matters

Participants have more “ownership” of the process, will generate more ideas, and will support eventual decisions when they have the opportunity to shape the process and the outcomes. Conversely, if participants feel their time is wasted or they are being used to rubber-stamp foregone conclusions, the process could seriously undermine trust and continued engagement. Unanswered phone calls and emails, promises made and not kept, actions taken in secret without a demonstrated need, all build distrust.

People are most likely to become involved in an engagement process under certain conditions, at the center of which is possibility: of being heard, of contributing to their community, and of creating change

Key Concepts

Meeting minutes refer to notes that closely reflect each comment made during a meeting.

A meeting summary is just that: a concise summary only of what happened during a meeting.

Some groups use a “sense of the meeting” to refer to a meeting summary that focuses on capturing key meeting themes and items requiring followup action.

Questions to Ask

Too many communities view their governing authorities as distant, uncaring, and out of touch. And that can be the case even when those authorities intend otherwise. How can we create engagement that is meaningful? How can we create processes that acknowledge and respond to community member questions, needs, concerns and ideas in timely and meaningful ways?

Asking the following questions can help in designing a process that is responsive to community and participant needs, concerns and interests:

  • Who in the community has been working on these issues? How may their work be reflected or honored in the engagement process?

  • Are there community members or participants who can help think through the purposes, agenda, appropriate locations and times, and other key elements of the process?

  • Is there sufficient support to ensure that the process can secure and respond to member and/or public input?

  • How will the results of the meeting(s) be used, and by whom? How may participants influence that use?

  • What sort of follow-up will occur following the meeting(s) to demonstrate the relevance of the engagement to any decision process?

Going Deeper

Charlottesville’s 2016 Blue Ribbon Commission on Race, Memorials and Public Spaces took place with some 17 open meetings held during a six-month time span. Although almost all meetings were recorded, the absence of meeting summaries meant there was no way for people to understand what the Commission had done without attending meetings or listening to the meeting recordings. This gap led to numerous inaccurate reports on social media of Commission actions. The absence of meeting summaries also led to the omission of some votes that were taken at the final meeting but not included in the final Commission Report published on the City’s website. Although there was a Commission email that members of the public could and did use to send comments and ideas to the Commission, responding to the emails was left up to individual Commission members. This left many members of the public who wrote the Commission with no formal or consistent way of knowing that their messages were received, much less considered.

Successful collaborations devolve power to the participants as much as possible. As a general rule, the greater the influence that participants have over the process, the more invested they will be in learning as well as creating and implementing group decisions.

Best practices to accomplish a responsive process include:

Ensure that the process is as transparent as can be. Reply to every concern, question and idea by acknowledging it and detailing how and why it may or may not shape decisions.

Give participants opportunities to review and provide input about all stages of the planning process. This can and usually should include items such as meeting agendas, locations, interim objectives, and speakers.

Adopt a participatory decision-making model, such as consensus, so that participants are empowered to shape and ratify decisions.

Ensure that all meetings are recorded and summarized in ways that are readable and accessible.

Ask for constructive feedback about the process regularly and in a variety of ways (e.g. plus/delta recap at the end of the meeting, questionnaire, online survey, email address to send feedback).

Avoid “decide, announce, and defend.” Instead, consult the community as early as possible in the planning phase. How?

Phone interviews;

Emails;

Visit existing groups to for ideas/ feedback about how they would like to be engaged;

Form a representative stakeholder advisory planning group

Resources

Following is an example from portions of a responsive meeting summary that details items that responded to the previous meeting and followup actions to be taken in response to this session:

VDOT Clarkton Bridge Treatment Scoping Meeting

February 22, 2017

Childrey Baptist Church

10:00 AM – 1:00 PM

Executive Summary

A second scoping meeting to discuss the future treatment of the Clarkton Bridge was held on Wednesday February 22nd at Childrey Baptist Church in Nathalie. The meeting was facilitated by the University of Virginia’s Institute of Environmental Negotiation (IEN. A list of participants is included with this document.

Recap of activities related to Clarkton Bridge

 provided an overview of VDOT’s efforts to gather the information requested at the September 2016 meeting, including responding to a request from  for documents that could be supplied to . Additionally,  and  met with  and  in November 2016 to discuss options for moving forward.

...

Next steps include:

•        VDOT will provide a list of pedestrian bridges in Virginia, as soon as it can be completed. (Included with this document)

•        VDOT will supply to.  a list of needed repairs that was generated in 2005, to be sent to

•        VDOT will explore whether it could store the disassembled bridge and, if so, whether a cost would be associated with this storage.

•        VDOT will set a date for a public meeting and/or another stakeholder meeting, and once that date is established it will be shared with the group.

•        All documents mentioned above will be shared with the group via the shared drive.